I can no longer see the large changes taking place that I first
experienced. The work has become much more tedious now that I am
getting close to the three quarter point. The ballast system is
completed with all valves and hoses in place for both the hard and
soft tanks. The generator is now ready to run with gauges, exhaust
and fuel lines in place. Building the sub without a complete set of
prints has proven to be quite a challenge and parts are constantly
assembled and disassembled to be sure of proper fit and to allow
room for the other components. It is truly a tremendous undertaking
and should not be started unless you have the time and the patience
to see it through. I have eleven hundred hours involved in the
construction at this point and I believe it will be another four or
five hundred before its ready to test. I am however testing the
systems for leaks as we proceed so that I don' t run into a major
problem later. It looks to me like we should see a mid summer
launch. |
||||||||||||
|
|
||||||||||||
|
|